Industrial

Power Generation Facility - Simple Cycle Expansion

Power Generation Facility - Simple Cycle Expansion

Update March 2018

Construction is coming to an end at Doswell Limited Partnership. Electric generating turbines has been installed and their housing structures have them completely enclosed. Control rooms, transformers and switch assemblies have been installed. High wire support towers are standing and have been connected into the electric grid. The buzz of electricity can be heard. The twin exhaust stacks have been completed.  Construction crews continue with fine details of equipment installation and calibration. The perimeter road installation has begun. Equipment testing will begin in a few weeks.  

 

 

New 150,000sf FedEx Ground Distribution Center

New 150,000sf FedEx Ground Distribution Center

Due to our knowledge of the area and good working relationship with Hanover County, The Westmoreland Company requested Resource’s services to bring a 150,000sf FedEx distribution center to Hanover County.